Question

Field 14 “Delivery/cash settlement location” in Table 2 of Annex IV of RTS 2 (transparency reference data), as amended by [Amending Regulation RTS 2], should be populated with a standard code (Energy Identification Code – “EIC”) for electricity and gas contracts. How should Field 14 “Delivery/cash settlement location” for electricity and gas contracts be reported for a) cash settled contracts; b) contracts for which an EIC is not available? [MiFID II and MiFIR transparency topics, Section 3, Question 25]

Answer

Field 14 “Delivery/cash settlement location” should be interpreted and reported in the same way for cash settled and physically settled contract with regards to electricity and gas contracts. For example, Field 14 “Delivery/cash settlement location” for a cash settled contract on German power should be reported in the same manner as if the contract was physically settled, i.e. with the EIC “10YDE-RWENET---I”. The list of available EIC is managed and maintained by ENTSO-E [1] . Regarding electricity and gas contracts for which an EIC is not available or not appropriate (for example, a market area outside the Energy Internal European Market, or a contract referencing an index), Field 14 “Delivery/cash settlement location” should be populated with an ad-hoc code meeting the following requirements: The format should be the same as the format of EIC, i.e. {ALPHANUM-16}; Generic values such as “CASH”, “UNKNOWN” or the name of the CCP clearing the contract should not be used; The text in the ad-hoc code should provide a- clear indication of the reference of the contract. Valid ad-hoc codes that are currently in use, are provided in the table below. You may contact data-statistics@esma.europa.eu to request an update of the list. Contract Ad-hoc code for Field 14 Added on Japanese Power Futures - Tokyo 10YJP-TOKYO---AR 31/03/2023 Japanese Power Futures - Kansai 10YJP-KANSAI--AR 31/03/2023 LNG Japan/Korea Futures JP-KR-JKM----LNG 31/03/2023   [1] https://www.entsoe.eu/data/energy-identification-codes-eic/eic-approved-codes/

This Q&A is published by European Securities and Markets Authority and is non-binding. It does not constitute legal advice. Updated weekly from official ESA sources.

Similar Q&As

More Q&As on this topic

📋 Track EU financial regulation continuously

Forseti monitors EU financial regulation and delivers personalised alerts anchored to verified official sources.

14-day free trial. No credit card required.